ID | 00070 | ||||||||
Name | Workdays (Duration) Definition | ||||||||
Available values |
|
||||||||
Default value | Only Weekdays (Excl. Public Holidays) | ||||||||
Description | With this setting you can define if public holidays and / or weekends should be counted as working days. | ||||||||
Prerequisite |
To visualize the differences we chose a period from 20.07.2016 to 21.08.2016 having one public holiday on the 01.08.2016.
The task is entered for all examples from 28.07.2016 with 7 working days.
Only Weekdays (Excl. Public Holidays)
Weekends and public holidays are not counted as working days - therefore the task will end on the 08.08.2016
Only Weekdays (Incl. Public Holidays)
Public holidays are counted as working days but not Weekends - therefore the task will end on the 05.08.2016
Weekdays And Weekends (Excl. Public Holidays)
Weekends counted as working days but not public holidays - therefore the task will end on the 04.08.2016
Weekdays And Weekends (Incl. Public Holidays)
Weekends and public holidays are counted as working days - therefore the task will end on the 03.08.2016